Every year the same thing happens. A drilling programme gets scheduled on a clean 10-week plan. Then somebody notices Ramadan lands in the middle, and Eid right after it, and half the crew will be away.
You can plan for it. It's not hard. But it needs doing before the programme is signed, not after.
Start with the calendar
Ramadan moves roughly ten to eleven days earlier each year because it follows the lunar calendar. For 2027 it's expected to begin in early to mid-February, with the exact date set by moon sighting. Don't hard-code a start date into a contract. Give yourself a window.
Eid al-Fitr follows Ramadan and usually brings a multi-day break, often longer once weekends are added. Eid al-Adha lands later in the year with its own holiday. Check the official government announcements close to each date.
What changes on site during Ramadan
The UAE's Ministry of Human Resources and Emiratisation (MoHRE) cuts normal working hours for private-sector staff by two hours a day during Ramadan, and it confirmed this again for Ramadan 2026. Companies may use flexible or remote schedules within the reduced hours. The ministry announces the arrangements each year, so check the notice for your own project window before you plan. Other GCC countries run their own variants, so a regional programme needs one calendar per country.
For a drilling crew, shorter hours change the maths.
- Fewer drilled metres per day. The usual setup and teardown time doesn't shrink, so the productive window shrinks more than proportionally.
- Shifted rhythm. Many crews move work to early morning and evening. Night drilling needs lighting, noise limits and a safety plan.
- Lower energy by afternoon. Heavy physical work, such as handling rods, needs more thought. Plan the hardest lifts early.
- Supply and delivery timing. Suppliers, labs and couriers may run reduced hours.
Don't treat any of this as a problem to be managed around people. It's a scheduling input, like weather.
Add the summer break
Ramadan isn't the only seasonal limit. In the UAE, MoHRE's midday break bans outdoor work in direct sunlight from 12:30 to 3:00 pm between 15 June and 15 September. It returned for the 22nd year in 2026. Check the ministry's notice each year for the current dates and any exemptions.
When Ramadan and summer overlapped in past years, crews lost a double chunk of the day. Right now Ramadan falls in winter, which is easier on heat, but the pattern shifts each year, so look at the actual overlap in your project window.
Heat affects the rig too. See maintaining a rig in extreme heat.
A scheduling approach that works
- Count working days, not calendar weeks. Subtract Ramadan reduction, Eid, Fridays and any summer midday stops.
- Add float to the critical path. Mobilisation, permits and lab turnaround all stretch in these periods.
- Front-load the heavy work. If the long holes can finish before Ramadan, do those first.
- Align lab and consultant availability. A drilling programme finishing the day before Eid can leave samples sitting for a week.
- Plan crew rotation. Leave and travel cluster around Eid. Confirm who is on site and who isn't.
- Set a fallback date. A programme that slips past Eid shouldn't slide a month.
Contract points worth fixing early
Write the seasonal assumptions into the programme. A drilling contract that silently assumes full working days all the way through invites a dispute later. Specify the working hours, what counts as a non-working day, and how delays from official restrictions are treated.
Our GCC safety and compliance guide covers the compliance side, and common rental mistakes lists the way bad hire terms go wrong. Rented rig? Agree who pays during the holiday gap.
Equipment choices that help
Faster setup helps when the window is short. Rigs that go from the truck to drilling quickly, and that switch between SPT and coring without swapping equipment, save hours each day. The MD600N lists an automatic SPT hammer and N-wireline coring on track or truck mounting, and the MD150N is rated to 150 m with N-wireline. See the full drills page and drilling tools.
Spares matter more when a part can't wait for a holiday to end. Keep the common wear items on site. MetaDrill rigs are built in the UAE, which helps with parts availability outside holiday periods.
An example programme, adjusted (illustration)
Say a client wants 20 boreholes drilled, each about 20 m deep, and your normal rate is two holes per working day.
On a normal calendar, that's ten working days.
Now put it through Ramadan. If shorter hours cut your productive time by roughly a fifth, two holes a day may become closer to one and a half, so the same job needs about thirteen days. Add the Eid break and a few days of float on both sides, and a ten-day job can stretch across three weeks of calendar time.
Numbers like these are only an illustration. Your own output per day will differ with depth, ground and crew. The method is what counts: take your normal rate, adjust it for the real working hours, count actual working days, then add float.
A short note on what to say to clients. Offer the revised timeline early, along with the reasoning. Most project managers accept a realistic schedule easily. What they don't accept is a delay announced halfway through the job.
Crew, welfare and safety
Fasting crews work in the heat with less water in the day. Heat illness is a serious risk for anyone, so site managers adjust the day to protect people. Common practices include scheduling heavy lifting early, providing shaded rest areas, and keeping water and cool spaces ready for break time after sunset. Check your company's and client's own guidance, and follow the official rules on working hours and heat.
Supervisors should also watch for fatigue near the end of the shift. Rod handling and rig set-up are physical tasks where a slip causes injuries. Shorter, earlier shifts with proper rest can be safer than long ones.
Sourcing and deliveries
Plan material orders around the calendar. Bits, rods, casing, grout and fuel deliveries may arrive later around Eid, and some suppliers close for several days. Order consumables a week or two ahead, and keep a small stock of the items that stop work if they run out.
If you're hiring a rig, agree the terms for holiday periods before you sign. See common rental mistakes for the contract points that trip people up.
Quick answers
Can night drilling make up lost time? Sometimes, if lighting, noise limits and safety plans allow. Check site rules and the client's requirements first.
How do I handle Eid in a contract? Name the likely dates as a window, state that official announcements decide the exact days, and define how delay is treated.
Does Ramadan stop drilling? No. Work continues with adjusted hours.
When is Ramadan in 2027? Expected in early to mid-February, depending on moon sighting.
Are there other seasonal limits? Yes. In the UAE, there's a midday outdoor work break in summer.
Planning a programme that crosses a holiday?
Send us the borehole schedule and the window. We'll suggest a rig and tooling set that gets the most from each working hour. See our site investigation services or contact us.
Question to the public:
How Ramadan, Eid and the summer midday break change drilling schedules in the UAE and GCC, with a practical planning checklist for contractors.