Permits for Geotechnical Drilling in the US and Canada
The rig is on the truck. The crew is booked. And the permit hasn't come through.
Nothing burns money like a drill sitting idle at the gate. Most delays on a geotechnical job have nothing to do with the ground. They come from paperwork nobody started early enough.
This guide lists the kinds of approvals a boring programme usually runs into, so you know what to ask for. It is not legal advice. Rules vary by state, province, county and municipality, and they change. Confirm each item with the authority that has jurisdiction.
If you want the standards side of things, read our regulations guide for the US and Canada. This post is about the practical application steps.
The usual categories
Think of permits as five buckets. Not every job needs all five.
1. Utility locates. In the US, you call 811 before you dig, which includes drilling. Canada has regional equivalents, such as provincial one-call centers. Request the locate well ahead of the start date, because marking takes days, not hours. And locate marks don't always catch private lines, so many crews also hire private utility locators.
2. Right-of-way and road permits. Drilling in or beside a public road usually needs permission from the road authority, plus traffic control plans. State DOT, county and city rules differ.
3. Driller or contractor licensing. Some states and provinces license drillers for certain work, especially water wells and some environmental or monitoring wells. Rules for geotechnical borings vary. Check before you bid a job in a new jurisdiction.
4. Environmental and land-use approvals. Wetlands, protected habitats, flood zones, contaminated land and conservation areas can all trigger extra review. Federal land has its own process.
5. Borehole closure. Many jurisdictions require specific methods for sealing or abandoning boreholes, to protect groundwater. Sealing with grout or bentonite is common, and the details can be set by regulation.
What changes by region
The US doesn't have one national permit system for boring. States set most of it, then counties and cities add more. Canada works the same way with provinces and territories in charge, plus municipal rules.
Practical result: a crew that works smoothly in one state can be caught out one county over. Keep a small checklist for each jurisdiction you work in, and update it when you learn something.
Timelines
We don't quote typical approval times, because they vary too much. A routine job on private land may need little more than a utility locate. A job on a state highway shoulder can take weeks.
What we can say: start every approval at the same time, not one after another. And build the permit lead time into the quote, so the client sees it before the programme starts.
Cold-weather add-ons
Northern jobs add seasonal issues. Frost laws that restrict heavy vehicles on roads in spring thaw can limit when a rig can travel. Winter work can mean extra safety planning. See frost line drilling for the winter side.
Safety paperwork
Alongside permits come safety obligations. Site-specific safety plans, hazard assessments, and operator training records are standard asks from owners and general contractors. OSHA in the US, and provincial occupational health authorities in Canada, set the legal frame. Check what your client expects on top of that.
Equipment and documentation
Some permit applications ask for equipment details: rig type, size, weight, and sometimes engine emissions. Having this on a spec sheet speeds things up. The MD600X product page lists the key figures, including a 173 HP John Deere Tier 4F engine and track mounting with wide shoes, which helps when a site manager asks about ground pressure. Confirm any weight figure with the manufacturer before putting it in an application.
For a quick overview of the machines, see our North America page.
A starter checklist
- Confirm the scope: number of borings, depths, locations
- Identify the land owner and any easements
- Request utility locates
- Check road authority and traffic control requirements
- Check environmental constraints on the site
- Confirm licensing in the jurisdiction
- Plan borehole closure and waste disposal
- Collect safety documents the client needs
- Put everything on the schedule with dates
Who pulls the permit?
This question causes more arguments than any technical one. In the contract, say who obtains each approval, who pays, and who bears the cost of delays.
On private projects, the owner or general contractor often handles site access and land-use items, while the driller handles the equipment-related items and the utility locate request. On public work, the agency may supply some approvals and expect the contractor to supply the others. Never assume. Write it down.
Delay clauses matter as well. If a permit takes longer than planned through no fault of the driller, standby time may be billable. Agree the rate up front. A rig on standby still costs money.
Closing holes properly
Every borehole eventually needs to be dealt with. Some are left open briefly for water-level readings. Others become monitoring wells. Most are sealed.
Sealing practice varies, but common approaches include filling the hole with grout or bentonite from the bottom up, and restoring the surface. Some jurisdictions set rules on materials, methods and records, especially where holes could create a path for contaminants to reach groundwater. Check the requirement for your jurisdiction, keep a record of what was done at each hole, and take photos.
If you drill near contaminated land, extra rules may apply to handling cuttings and fluids. Ask the environmental consultant before you start.
A note on records
Keep every permit, approval and locate ticket in one place, on paper or digital, and carry copies to the site. Inspectors and clients ask to see them, and a missing document can stop work. Record the date of each utility locate request, since the marks may expire or get disturbed.
Quick answers
How early should I request a utility locate? As early as the rules allow, and well before the start date. Marking can take several days, and some areas have rules on how long marks remain valid. Check the local one-call center.
Do monitoring wells need extra approval? Often yes. Wells left in the ground for longer than a few days commonly fall under well-construction and registration rules. Ask the local environmental or water authority.
What if I find contamination while drilling? Stop, secure the area, and follow the project's environmental plan. Report it as the contract and the law require.
Do I need a permit for a soil boring? Sometimes. A utility locate nearly always. Other permits depend on where the site is.
Who issues drilling permits? State, province, county or city authorities, depending on the work.
Who is responsible for permits, the client or the driller? The contract says. Clarify before the job starts.
For the thaw season side, see spring thaw drilling conditions.
Working on both sides of the border? See US vs Canada drilling differences.